Ongoing Project | Project Management Consultancy
Bothe Wind farm Pvt Ltd
Started in Jan 2013 having in Spread over three different villages in Taluka MAN, Dis: Satara state: Maharashtra this is one of the prestige’s and gigantic project executed by SNES team. This project comprises of EPC and civil setup for more than 120 no’s of Suzlon& Vestas 2.2 MW WTGs. Each foundation need almost 550m3 of concrete which is been casted in record time of 10Hr. Deploying a team of more than 130 personnel, this project is expected to be over in March 2014
Details
- Client: Bothe Wind farm Pvt Ltd
- Project Title: PMC for 2.2MW windmill (VESTAS & SUZLON) EPC (120 No’s)
- Location: Satara
- Date: Jan, 2013